March 13, 2013
Phase 1 construction of the causeway overpass is anticipated to begin in late March and continue until July 2013, with expected completion in late 2014.
-
March 07, 2013
Port Metro Vancouver is beginning site preparation and preliminary work in and around Roberts Bank to help facilitate future construction of the Deltaport Terminal, Road and Rail Improvement Project. As part of this work, there will be a power outage on the Roberts Bank causeway for approximately eight hours on March 17, 2013.
-
February 28, 2013
Port Metro Vancouver is continuing field studies in March 2013 as part of ongoing environmental and technical work for the proposed Roberts Bank Terminal 2 Project.
-
February 01, 2013
Port Metro Vancouver is continuing field studies in February 2013 as part of ongoing environmental and technical work for the proposed Roberts Bank Terminal 2 Project.
-
January 24, 2013
Port Metro Vancouver is pleased to receive funding from the Government of Canada through the Asia-Pacific Gateway and Corridor Initiative (APGCI).
-
January 17, 2013
Port Metro Vancouver is beginning site preparation and preliminary work in and around Roberts Bank to help facilitate future construction of the Deltaport Terminal, Road and Rail Improvement Project.
-
January 09, 2013
Port Metro Vancouver is conducting sediment characterization in January and February 2013 as part of ongoing technical work for the proposed Roberts Bank Terminal 2 Project.
-
January 01, 2013
Port Metro Vancouver is continuing field studies in January 2013 as part of ongoing environmental and technical work for the proposed Roberts Bank Terminal 2 Project.
-
December 05, 2012
The Deltaport Terminal, Road and Rail Improvement Project’s environmental assessment review is now complete.
-
December 04, 2012
Port Metro Vancouver is conducting field studies in and around Roberts Bank to gather information and data as part of the technical work for the Deltaport Terminal, Road and Rail Improvement Project.
-
December 03, 2012
Port Metro Vancouver is continuing field studies in December 2012 as part of ongoing environmental and technical work for the proposed Roberts Bank Terminal 2 Project.
-
November 01, 2012
Port Metro Vancouver is continuing field studies in October 2012 as part of ongoing environmental and technical work for the proposed Roberts Bank Terminal 2 Project.
-
October 22, 2012
Port Metro Vancouver has commenced Project Definition Consultation regarding the proposed Roberts Bank Terminal 2 Project.
-
October 04, 2012
Port Metro Vancouver is undertaking Project Definition Consultation regarding the proposed Roberts Bank Terminal 2 Project between October 22, 2012 and November 30, 2012.
-
October 04, 2012
Port Metro Vancouver is continuing field studies in October 2012 as part of ongoing environmental and technical work for the proposed Roberts Bank Terminal 2 Project.
-
September 06, 2012
Port Metro Vancouver is continuing field studies in September 2012 as part of ongoing environmental and technical work for the proposed Roberts Bank Terminal 2 Project.
-
August 29, 2012
As part of the environmental assessment for the Deltaport Terminal, Road and Rail Improvement Project, Port Metro Vancouver has posted the Responses to Public Comments Regarding the CEAA Screening-Level Environment Assessment Report.
-
August 01, 2012
Port Metro Vancouver is continuing field studies in August 2012 as part of ongoing environmental and technical work for the proposed Roberts Bank Terminal 2 Project.
-
July 25, 2012
Port Metro Vancouver is continuing work on the environmental assessment and permitting process for the Deltaport Terminal, Road and Rail Improvement Project.
-
July 03, 2012
Port Metro Vancouver is continuing field studies in July 2012 as part of ongoing environmental and technical work for the proposed Roberts Bank Terminal 2 Project.
-
June 01, 2012
Port Metro Vancouver is continuing field studies in June 2012 as part of ongoing environmental and technical work for the proposed Roberts Bank Terminal 2 Project.
-
May 17, 2012
As part of the Container Capacity Improvement Program, Port Metro Vancouver is conducting Geotechnical Investigations in and around Roberts starting in May 2012.
-
May 01, 2012
Port Metro Vancouver is continuing field studies in May 2012 as part of ongoing environmental and technical work for the proposed Roberts Bank Terminal 2 Project.
-
April 11, 2012
As part of the environmental assessment for the Deltaport Terminal, Road and Rail Improvement Project, Port Metro Vancouver has posted the CEAA Screening-Level Environment Assessment Report for public comment.
-
April 05, 2012
Port Metro Vancouver is conducting field studies in April 2012 as part of ongoing environmental and technical work for the proposed Roberts Bank Terminal 2 Project.
-
April 04, 2012
Port Metro Vancouver has made available a number of consultation summary documents for the Deltaport Terminal, Road and Rail Improvement Project.
These include the Response to Public Comments Regarding the Project Description, Consultation Summary Report and Consideration of Consultation Input.
-
February 14, 2012
As part of the Container Capacity Improvement Program, Port Metro Vancouver is conducting topographic land surveys in and around Roberts Bank to gather data to assist in the detailed engineering design for the road and rail improvements at Deltaport.
-
January 08, 2012
Port Metro Vancouver undertook public consultation for the Deltaport Terminal, Road and Rail Improvement Project between November 21, 2011 and January 6, 2012. Communities, stakeholders and the public were provided opportunities to learn about the project and provide input through a number of multi-stakeholder meetings, open houses and an online feedback form.
-
November 22, 2011
Port Metro Vancouver is undertaking public consultation regarding the Deltaport Terminal, Road and Rail Improvement Project between November 21, 2011 and January 6, 2012. We are providing opportunities for input from communities, stakeholders and the public through a number of multi-stakeholder meetings, open houses and an online feedback form.
-
November 21, 2011
As part of the Container Capacity Improvement Program, Port Metro Vancouver is conducting Geotechnical Investigations in and around Roberts Bank in late November and early December 2011.
-
September 15, 2011
As part of the Container Capacity Improvement Program, Port Metro Vancouver is initiating an underwater survey in the vicinity of Roberts Bank from mid to late September 2011.
-
September 07, 2011
As part of the Container Capacity Improvement Program, Port Metro Vancouver is initiating Geotechnical Investigations along the Roberts Bank causeway in early September 2011.
-
August 03, 2011
As part of the Container Capacity Improvement Program, Port Metro Vancouver is conducting ecology field studies in and around Roberts Bank in mid to late August 2011.
-
July 27, 2011
As part of the Container Capacity Improvement Program, Port Metro Vancouver is conducting a marine geophysical investigation in and around Roberts Bank to gather more information and data to assist in evaluating the proposed Roberts Bank Terminal 2 Project.
-
July 20, 2011
As part of the Container Capacity Improvement Program, Port Metro Vancouver is undertaking noise monitoring field surveys in and around Roberts Bank to gather information and data to assist in evaluating potential road and rail improvements at Deltaport.
-
July 06, 2011
To gather more information and data to assist in evaluating road and rail improvements to the Deltaport Intermodal Yard, Port Metro Vancouver is undertaking ecology field surveys in mid to late July 2011.
-
June 22, 2011
To gather more information and data to assist in evaluating the proposed Roberts Bank Terminal 2 Project, Port Metro Vancouver is continuing oceanographic field studies, which began in February 2011.
-
June 08, 2011
The Container Capacity Improvement Program is Port Metro Vancouver’s long-term strategy to reliably support growing international trade in an efficient and sustainable manner.
-
May 18, 2011
Port Metro Vancouver is initiating ocean and sea bed (bathymetry) and land (topography) surveys beginning in mid-late May 2011 as part of the project definition phase of the proposed Roberts Bank Terminal 2 project.
-
April 20, 2011
Port Metro Vancouver is initiating geotechnical investigations beginning in spring 2011 as part of the project definition phase of the proposed Roberts Bank Terminal 2 project.
-
February 23, 2011
To gather more information and data to assist in evaluating the proposed Roberts Bank Terminal 2 Project, Port Metro Vancouver is initiating oceanographic field studies beginning in February 2011.