Deltaport Terminal, Road and Rail Improvement Project

  • Project Update – January 2014

    Jan 20, 2014, 09:42 AM

    The Deltaport Terminal, Road and Rail Improvement Project is a series of improvements to the existing Deltaport Terminal at Roberts Bank in Delta, B.C. The causeway overpass is the first component of the project to be built. Construction began in March 2013, and is expected to reach completion in late 2014.

    Phase 4 construction activities will run from January to March 2014 and will be limited to the vicinity of the planned causeway overpass site.

    Learn more

  • Project Update - August 2013

    Aug 16, 2013, 13:57 PM
    Phase 2 and 3 construction is anticipated to begin in late August and continue until October 2013, with expected completion of the causeway overpass in late 2014.
  • Project Update - March 2013

    Mar 13, 2013, 13:53 PM
    Phase 1 construction of the causeway overpass is anticipated to begin in late March and continue until July 2013, with expected completion in late 2014.
  • Notice of Power Outage at Roberts Bank

    Mar 7, 2013, 14:19 PM
    Port Metro Vancouver is beginning site preparation and preliminary work in and around Roberts Bank to help facilitate future construction of the Deltaport Terminal, Road and Rail Improvement Project. As part of this work, there will be a power outage on the Roberts Bank causeway for approximately eight hours on March 17, 2013.
  • DTRRIP Receives Funding from the Government of Canada

    Jan 24, 2013, 09:19 AM
    Port Metro Vancouver is pleased to receive funding from the Government of Canada through the Asia-Pacific Gateway and Corridor Initiative (APGCI).
  • Transmission Line Relocation

    Jan 17, 2013, 09:36 AM
    Port Metro Vancouver is beginning site preparation and preliminary work in and around Roberts Bank to help facilitate future construction of the Deltaport Terminal, Road and Rail Improvement Project.
  • Environmental Assessment Review Complete

    Dec 5, 2012, 09:48 AM
    The Deltaport Terminal, Road and Rail Improvement Project’s environmental assessment review is now complete.
  • Field Studies at Roberts Bank in December 2012

    Dec 3, 2012, 10:02 AM
    Port Metro Vancouver is continuing field studies in December 2012 as part of ongoing environmental and technical work for the proposed Roberts Bank Terminal 2 Project.
  • Responses to Public Comments Available

    Aug 29, 2012, 16:00 PM
    As part of the environmental assessment for the Deltaport Terminal, Road and Rail Improvement Project, Port Metro Vancouver has posted the Responses to Public Comments Regarding the CEAA Screening-Level Environment Assessment Report.
  • Responses to Public Comments Available

    Aug 29, 2012, 10:28 AM
    As part of the environmental assessment for the Deltaport Terminal, Road and Rail Improvement Project, Port Metro Vancouver has posted the Responses to Public Comments Regarding the CEAA Screening-Level Environment Assessment Report.
  • DTRRIP Project Update - July 2012

    Jul 25, 2012, 13:28 PM
    Port Metro Vancouver is continuing work on the environmental assessment and permitting process for the Deltaport Terminal, Road and Rail Improvement Project.
  • Geotechnical Investigations

    May 17, 2012, 13:41 PM
    As part of the Container Capacity Improvement Program, Port Metro Vancouver is conducting Geotechnical Investigations in and around Roberts starting in May 2012.
  • DTRRIP CEAA Report Available for Public Comment

    Apr 11, 2012, 11:00 AM
    As part of the environmental assessment for the Deltaport Terminal, Road and Rail Improvement Project, Port Metro Vancouver has posted the CEAA Screening-Level Environment Assessment Report for public comment.
  • Consultation Summary Documents Available

    Apr 4, 2012, 17:48 PM
    Port Metro Vancouver has made available a number of consultation summary documents for the Deltaport Terminal, Road and Rail Improvement Project. These include the Response to Public Comments Regarding the Project Description, Consultation Summary Report and Consideration of Consultation Input.
  • Topographic Land Survey

    Feb 14, 2012, 12:00 PM
    As part of the Container Capacity Improvement Program, Port Metro Vancouver is conducting topographic land surveys in and around Roberts Bank to gather data to assist in the detailed engineering design for the road and rail improvements at Deltaport.
  • Consultation Closes for Deltaport Terminal, Road and Rail Improvement Project

    Jan 8, 2012, 08:00 AM
    Port Metro Vancouver undertook public consultation for the Deltaport Terminal, Road and Rail Improvement Project between November 21, 2011 and January 6, 2012. Communities, stakeholders and the public were provided opportunities to learn about the project and provide input through a number of multi-stakeholder meetings, open houses and an online feedback form.
  • Consultation Commences for Deltaport Terminal, Road and Rail Improvement Project

    Nov 22, 2011, 18:00 PM
    Port Metro Vancouver is undertaking public consultation regarding the Deltaport Terminal, Road and Rail Improvement Project between November 21, 2011 and January 6, 2012. We are providing opportunities for input from communities, stakeholders and the public through a number of multi-stakeholder meetings, open houses and an online feedback form.
  • Geotechnical Investigations

    Nov 21, 2011, 18:17 PM
    As part of the Container Capacity Improvement Program, Port Metro Vancouver is conducting Geotechnical Investigations in and around Roberts Bank in late November and early December 2011.
  • Geotechnical Investigations

    Sep 7, 2011, 00:00 AM
    As part of the Container Capacity Improvement Program, Port Metro Vancouver is initiating Geotechnical Investigations along the Roberts Bank causeway in early September 2011.
  • Noise Monitoring Field Studies

    Jul 20, 2011, 00:00 AM
    As part of the Container Capacity Improvement Program, Port Metro Vancouver is undertaking noise monitoring field surveys in and around Roberts Bank to gather information and data to assist in evaluating potential road and rail improvements at Deltaport.

Feedback? Inquiry?

Contact Us

Stay updated!

Sign up for our newsletter to receive periodic updates on the Deltaport Terminal, Road and Rail Improvement Project.

Back to home

Please Upgrade Your Browser

This site's design is only visible in a graphical browser that supports web standards, but its content is accessible to any browser or Internet device.