December 22, 2010

Final DP3 Project Newsletter

To read the final DP3 Project Update Newlsetter, please click here.

 

September 23, 2010

2009 Adaptive Management Strategy Annual Report now available

The Deltaport Third Berth Project Adaptive Management Strategy (AMS) and Summary Information Sheet are now available on the DP3 Project Website.

 


 

January 19, 2010

Deltaport's new third berth officially opens

On January 18, Global Container Terminals and Port Metro Vancouver, along with government officials, officially opened the new $400 million third berth at Deltaport container terminal. Click here to read press release.

DP3 Project Updates

  • December 11, 2009 - Removal of excavation material during evening hours

  • November 16, 2009 - Public information sessions and project newsletter

  • October 26, 2009 - 2008 Adaptive Management Strategy Annual Report Now Available

  • October 7, 2009 - Night work required for East Causeway Habitat Compensation Project

  • September 15, 2009 - Paving Activities and Lighting Tests

  • August 19, 2009 - Deltaport Crane Offloading

  • July 7, 2009 - DCLC Appoints New Members to Replace Existing Positions

  • June 10, 2009 - Final Preload Removal

  • May 27, 2009 - East Causeway Habitat Compensation Project

  • May 27, 2009 - Night-time Paving Activities

  • May 27, 2009 - Public Information Sessions

  • May 27, 2009 - DP3 Project Update Newsletter

  • May 15, 2009 - DCLC Call for Community Applications

  • April 30, 2009 – Notification of Minor Spill Incident

  • April 22, 2009 - Removal of Excess Preload from DP3 – Part 2

  • February 19, 2009 - Additional work scheduled outside of daytime hours

  • December 29, 2008 - Removal of Surplus Preload from DP3 Construction Site to locations within Delta

  • November 24, 2008 - Public Information Event

  • October 24, 2008 - Port Metro Vancouver ceases ocean disposal operations at Roberts Bank related to Deltaport Third Berth Project

  • September 8, 2008 - 2007 Adaptive Management Strategy Annual - Frequently Asked Questions

  • July 28, 2008 - 2007 Adaptive Management Strategy Annual Report and Summary Information Sheet

  • June 11, 2008 - Highway 17 Improvements underway as part of Deltaport Third Berth Project

  • May 21, 2008 - Deltaport Third Berth Project (DP3) Public Open House and Project Newsletter

  • March 14, 2008 - Becker Densification Testing This Weekend

  • March 12, 2008 - Update on DP3 Densification Probe Incident

  • March 5, 2008 - Update on DP3 Densification Probe Incident

  • March 4, 2008 - DP3 Densification Probe Incident

  • November 20, 2007 - UPDATE on Barge Grounding Incident

  • November 14, 2007 - Public Open House and Updated DP3 Newsletter

  • November 13, 2007 - Barge Grounding Incident

  • November 2, 2007 - Wood Pile Placement

  • October 5, 2007 - Update on Deltaport Third Berth Project Construction Activities

  • August 13, 2007 - UPDATE on Disposal of Clean Dredge Material Outside the Permitted Disposal Location

  • August 2, 2007 – Port Investigation of Improper Ocean Disposal Related to DP3 Project and BCTC Transmission Line

  • May 17, 2007 - Upcoming Public Events for the Deltaport Third Berth Project

  • May 10, 2007 - Scientific Advisory Committee

  • March 21, 2007 - Dredging

  • February 13, 2007 - Deltaport Project Update - Winter 2007

  • February 8, 2007 - Deadline for DCLC applications has been extended

Learn more

On portmetrovancouver.com

Filling the caissons

Filling the caissons at DP3, 2008

Gravel fill is placed into the caissons once they are placed in the final location. A caisson is the cement structure that is used to create the base of the berth structure.